Thwake Dam to be commissioned in April 2027

htepk2fxkaa5dje
htepk2fxkaa5dje

The government has announced that the KSh37 billion Thwake Dam will be commissioned in April 2027, three months to the August General Elections. On Wednesday, State Department for Water and Sanitation Principal Secretary Julius Korir, chaired a meeting attended by African Development Bank (AfDB) officials to review progress on the Thwake Multipurpose Water Development Project.

The discussions focused on financing, construction timelines, audit recommendations, environmental safeguards and community engagement. The meeting reviewed the status of ongoing civil works and measures to address cash flow constraints affecting pending works, including the processing of Interim Payment Certificate No. 29. The meeting also considered measures to sustain the pace of construction as the project approaches key milestones.

The Project’s critical path and implementation schedule were also reviewed, with impoundment targeted for late January 2027 and full commissioning scheduled for April 2027. An updated implementation matrix is being finalised to align decision points and responsibilities with recommendations arising from international audit reviews.

The meeting further considered environmental safeguards, particularly measures to manage upstream sedimentation and protect the long-term capacity of the reservoir. Discussions also focused on resolving outstanding concerns involving Project Affected Persons, with efforts ongoing to achieve full agreement and complete compensation clearance.

The Thwake Multipurpose Dam is a major water infrastructure project being developed at the confluence of the Thwake and Athi rivers, on the border of Makueni and Kitui counties in Kenya. The idea for the dam dates back to the 1992 National Water Master Plan, which identified Thwake as one of three sites in the Athi River Basin with potential for water supply, irrigation and power generation.

The Kenyan government subsequently developed the Thwake Multipurpose Water Development Programme as a response to persistent water shortages in the semi-arid Lower Eastern region. Phase One involves construction of an 80.5-metre-high concrete-faced rockfill dam with a storage capacity of about 688 million cubic metres. The construction contract, valued at KSh36.97 billion, was signed with China Gezhouba Group Company (CGGC) in November 2017, with construction commencing on 27 March 2018.

The project is being jointly financed by the Government of Kenya and the African Development Bank (AfDB) Group, with additional financing approved as construction progressed. In June 2026, the AfDB approved an additional €68.39 million to help complete Phase One, alongside €15 million in counterpart funding from the Kenyan Government.

The wider Thwake programme is planned in four phases and is intended to address several needs simultaneously: provide water for domestic and livestock use, support irrigation and food production, regulate Athi River flows for flood control and drought mitigation, supply water to about 1.3 million people, and eventually support approximately 20 MW of hydropower generation.

The irrigation component is planned to serve about 40,000 hectares (100,000 acres), while the water-supply component is designed to provide approximately 150,000 cubic metres of treated water per day to communities in Kitui and Makueni and Konza Technopolis in Machakos County. As of June 2026, the AfDB reported Phase One construction at approximately 90% complete.