Moi’s bridge–Matunda water project nears completion

hulqf7kxkaaoara
hulqf7kxkaaoara

Construction of the Moi’s Bridge–Matunda Water Supply Project has reached 66 per cent completion, with the government working to accelerate implementation of the infrastructure expected to serve approximately 104,000 people across Uasin Gishu, Kakamega and Trans Nzoia counties by 2040.

Principal Secretary for Water and Sanitation Julius Korir inspected the project alongside Water Secretary Eng. Samuel Alima to assess progress on key components, including the water intake, installation of the raw water pipeline and construction of the water treatment plant.

The inspection followed the commissioning of the Kapyego Water Project by President William Ruto, as the government continues to implement water infrastructure projects aimed at improving service delivery in different parts of the country.

The Moi’s Bridge–Matunda project is expected to benefit 23,112 households by improving the reliability of water supplies for domestic consumption, businesses and public institutions. Its completion is also expected to support public health, sanitation and economic activities in the beneficiary communities.

According to the Ministry of Water and Sanitation’s National Water and Sanitation Strategy, the wider water supply and sewerage investment is estimated to cost KSh 3.3 billion, including supervision expenses.

The strategy allocates approximately KSh 1.403 billion to water supply infrastructure and KSh 1.798 billion to sewerage systems, reflecting the project’s dual focus on improving water services and managing wastewater in the growing towns of Moi’s Bridge and Matunda.

However, a separate Ministry draft Water and Sanitation Sub-Sector Report lists Lot 1 of the project at an estimated cost of KSh 2 billion, with completion expected by December 2027. The report recorded 10 per cent completion as of June 2025 and identified slow contractor progress and low budget allocations among the challenges affecting implementation.

Government budget records also indicate an allocation of KSh 400 million for the project in 2026. This represents the allocation for the financial year rather than the total cost of the wider investment.

The different figures relate to separate budget and project descriptions, making it important to distinguish the overall water and sewerage investment from the cost of an individual project lot and annual funding.

The planned infrastructure includes water abstraction, treatment and transmission facilities to support distribution to the targeted communities. Once operational, the system is expected to strengthen the supply network and help meet rising demand associated with population growth and expanding economic activities.

The sewerage component will also help improve wastewater management in Moi’s Bridge and Matunda, reducing the risk of environmental pollution and supporting better sanitation as the towns develop.

During the inspection, Korir and Alima assessed ongoing works as implementation teams continued towards completion. Sustained construction progress, adequate funding and proper maintenance will be essential to ensuring that the investment delivers reliable services over the long term.

The project is expected to strengthen water security, improve sanitation and support livelihoods across the three counties, with its long-term benefits depending on timely completion and effective operation of the infrastructure.